Deals
The AI buildout is a lease book as much as a model race: megawatts, GPU queues, server backlogs, and the landlords who sit between the lab and the substation. This page tracks those deals as they appear in The Aigentic — with nulls for unknowns, not guesses.
Filter by text, status, who, or counterparty. Sort by announced date (newest first by default), who, or capacity. A backlog is labeled as a backlog; a lease is labeled as a lease. Source links go to the Daily edition or the outlet that carried the print.
Not investment advice. Sourced from public reports; figures can lag or get revised.
Status
Showing 48 of 48 deals
New Era Energy & Digital (TCDC PowerCo)
Sep 21, 2026
Announced · 20-year power purchase agreement (Phase 1)
Minimum 200 MW up to 207 MW for Phase 1; power from Vistra's adjacent 1,180 MW Odessa gas plant; expected available Q3 2027; campus planned to scale toward 1.4 GW over time (493-acre site)
- Counterparty
- Luminant ET Services (Vistra affiliate)
- Where
- Texas Critical Data Center, Odessa / Permian Basin, Texas, US
- Amount
- —
- MW
- 207
- GPUs
- —
Company PR + MarketWatch/RTT Sep 21, 2026. mw set to the contracted maximum (207); minimum is 200. Vistra also gets a 5% non-voting interest in the powered project portion plus ROFR/ROFO on future development. amountUsd null (not disclosed). Full-campus 1.4 GW is planned scale, not contracted Phase 1.
Sharon AI
Sep 21, 2026
Announced · Long-term AI data center customer / capacity agreement (SYD1 Stage 1)
~8,200 NVIDIA Blackwell Ultra GPUs (HGX B300) expected; initial operations targeted Q4 2026; SYD1 planned as 100 MW+ campus; Stage 1 reuses existing DC building
- Counterparty
- GreenSquare
- Where
- SYD1 campus, Norwest Business Park, Western Sydney, NSW, Australia
- Amount
- —
- MW
- —
- GPUs
- 8,200
GreenSquare/techpartner/w.media Sep 21, 2026. Financial terms and contracted MW not disclosed — mw/amountUsd left null. Campus pipeline cited as 100 MW+ at SYD1 and >1 GW broader GreenSquare portfolio; those are campus/pipeline figures, not Sharon's contracted allotment.
West Texas data center operator (unnamed; contracted with investment-grade hyperscaler; GPU designer as lease guarantor)
Sep 21, 2026
Announced · Six-year behind-the-meter baseload power supply (incl. balance of plant)
76 MW behind-the-meter; ~40 reciprocating natural-gas generation units; deploy Q4 2026 scaling into Q1 2027; revenue expected from Q1 2027
- Counterparty
- Kodiak Gas Services
- Where
- West Texas, US
- Amount
- —
- MW
- 76
- GPUs
- —
Kodiak IR PR Sep 21, 2026. Operator, hyperscaler, and GPU-designer guarantor not named. amountUsd null. Kodiak's second long-term primary-power contract to a data center.
Google
Sep 21, 2026
Announced · Nuclear uprate subscription (NU-1 tariff / ZECs)
~96 MW new nuclear capacity via EPUs on Georgia Power’s owned share of Vogtle and Hatch; ~$900M projected customer benefits over unit life (not Google payment)
- Counterparty
- Georgia Power
- Where
- Plants Vogtle and Hatch, Georgia, US
- Amount
- —
- MW
- 96
- GPUs
- —
Georgia Power press release Sep 21, 2026 (PSC filings Docket 44280, 56002). Subject to Georgia PSC approval. Google subscribes to new NU-1 tariff and receives Zero-Emission Credits for the uprate output; structure protects non-participating customers from incremental uprate cost. Hatch 1&2 EPU still needs PSC approval; Vogtle 1&2 EPU was approved in 2025 IRP. NRC license amendments still required. $900M figure is projected customer benefits, not disclosed Google spend — amountUsd left null.
Amazon Web Services
Sep 18, 2026
Announced · Data center lease + renewable PPAs (binding MoU)
300 MW first phase (four 75 MW units); explore up to 1 GW; 15-year lease once built; PPC ~€1.2B first-phase build
- Counterparty
- PPC (Public Power Corporation of Greece / ΔΕΗ)
- Where
- Agios Dimitrios (Kozani / Western Macedonia), Greece
- Amount
- —
- MW
- 300
- GPUs
- —
Binding MoU (regulated Athens Exchange disclosure also filed). AWS leases and runs IT; PPC owns buildings/land/energy infra and supplies renewable PPAs (>10 years). Expansion to 1 GW optional, needs further definitive agreements. First 300 MW targeted operational by end-2028; construction could begin end-2026. €1.2B is PPC first-phase capex, not lease contract value — amountUsd left null.
Oracle
Sep 17, 2026
Announced · Virtual power purchase agreement (VPPA)
433 MW from existing Panther Creek I–III wind farms; part of Oracle’s broader >1.7 GW Texas carbon-free portfolio
- Counterparty
- RWE Americas (Panther Creek I, II, III wind)
- Where
- West Texas (Sterling, Howard, Glasscock counties), US — ERCOT; supports Oracle data centers
- Amount
- —
- MW
- 433
- GPUs
- —
RWE press release Sep 17, 2026. VPPA supplies Texas grid in support of Oracle data-center operations; Panther Creek farms previously repowered. Oracle cites goal to match 100% of AI data-center electricity with carbon-free power by 2035. amountUsd not disclosed.
Oracle
Sep 17, 2026
Announced · Renewable energy supply agreements (wind / ERCOT)
Up to 568 MW renewable electricity from ENGIE wind resources serving ERCOT; part of Oracle’s broader >1.7 GW Texas carbon-free portfolio
- Counterparty
- ENGIE North America
- Where
- Texas, US (ERCOT); supports Oracle Texas / AI data-center operations
- Amount
- —
- MW
- 568
- GPUs
- —
ENGIE North America PR via PR Newswire Sep 17, 2026. Portfolio of wind resources; more than 500 MW / up to 568 MW. Dollar value and contract term not disclosed. Clearway also named in secondary coverage of the >1.7 GW Oracle Texas portfolio but no Clearway-primary MW disclosure found for a separate row.
Anthropic
Sep 16, 2026
Announced · Data center lease (first Australia site; inference capacity)
Planned 2.16 GW campus; ~A$32 billion development; online from 2027 (subject to FIRB)
- Counterparty
- Zerra DC (Singapore-based developer)
- Where
- Western Downs Digital Park near Dalby, Queensland, Australia (~250 km from Brisbane)
- Amount
- —
- MW
- —
- GPUs
- —
First Anthropic Australia data-centre lease per Reuters (sources). Campus planned by Zerra DC; Anthropic/Zerra declined comment. Subject to Foreign Investment Review Board approval. ABC/Brisbane Times cite ~A$32B campus cost; Reuters cites 2.16 GW total planned capacity. Inference use, not training. Do not treat A$ as USD.
Perplexity
Sep 15, 2026
Announced · Multi-year AI cloud compute offtake (training + managed inference)
Dedicated NVIDIA GB300 NVL72 clusters for training; production via Crusoe Managed Inference; MW, GPU count, and dollar value not disclosed
- Counterparty
- Crusoe
- Where
- Crusoe Cloud (sites undisclosed in reporting)
- Amount
- —
- MW
- —
- GPUs
- —
Bloomberg Sep 15, 2026 + Crusoe GlobeNewswire same day. Multi-year partnership for full model lifecycle on Crusoe Cloud; Crusoe also adopts Perplexity Enterprise for ~1,800 employees (software side, not capacity). Separate from Jane Street × Crusoe offtake already on tracker.
Bitdeer AI
Sep 14, 2026
Announced · 10-year data center services agreement (AI Cloud facility lease)
65.1 MW A202 IT load; energization targeted Q3 2027; with 21.7 MW A201 campus totals 86.8 MW
- Counterparty
- Unnamed data-center services landlord (same Johor Bahru campus as A201)
- Where
- Johor Bahru, Malaysia (existing Bitdeer AI campus with A201)
- Amount
- —
- MW
- 65.1
- GPUs
- —
Bitdeer AI company PR via GlobeNewswire Sep 14, 2026 (republished on FinancialContent). Largest single SEA capacity add; liquid-cooled rack-scale NVIDIA GB300 NVL72 / Vera Rubin capable. Facility-level DC lease only — no named end-customer offtake for A202 disclosed at announcement. amountUsd left null (pipeline figure is company-wide, not this lease).
Bell Canada (Bell AI Fabric)
Sep 14, 2026
Announced · AI data center campus expansion (non-binding MOU)
Pathway to 1.2 GW hub: existing ~300 MW under construction on provincial grid + up to 900 MW additional under Bring Your Own Power (partner gas generation); >$50B / ~$52.5B total capital figure cited including tenant compute and power gen
- Counterparty
- Government of Saskatchewan
- Where
- Near Regina (R.M. of Sherwood), Saskatchewan, Canada
- Amount
- $52.5B
- MW
- —
- GPUs
- —
Saskatchewan government news release Sep 14, 2026 (also Bell / CNW coverage Sep 15). Non-binding MOU — expansion subject to customer commitments, commercial agreements, permits, and environmental approvals. amountUsd is the reported ~$52.5B / >$50B prospective total capital (campus + tenant compute + power), not a signed lease NPV. 300 MW phase already under construction; this row captures the expansion-to-1.2 GW announcement.
Anthropic
Sep 13, 2026
Under construction · GPU services / compute lease (six-year, three tranches)
Up to $13.7B over six years; site planned ~120 MW expandable to ~180 MW; ops targeted early 2027 / Q1 2027
- Counterparty
- RUM Group (ex-Rumble; Northern Data / Quake AI)
- Where
- Maysville, Georgia, US (Banks/Jackson counties)
- Amount
- $13.7B
- MW
- 120
- GPUs
- —
The Information (Sep 13, 2026) identified Anthropic as the previously unnamed customer in RUM Group's Aug 24, 2026 8-K; neither Anthropic nor RUM had publicly confirmed at TECHi's publish time. Commercial agreement signed Aug 23 for GPU access/services at Maysville in three ~equal tranches (~$13.7B total); third tranche contingent on customer approval of delivery date. Customer also gets warrant for up to ~50.8M RUM Class A shares at $0.01. RUM disclosed it does not yet have financing to build the facility/buy GPUs. MW/acres from Northern Data's Dec 2024 Maysville campus plan (120 MW near-term, expand to 180 MW, 63 acres) as cited by DCD; do not invent GPU count.
G42 (UAE AI campus / Stargate UAE)
Sep 11, 2026
Under construction · AI data center campus redesign (5 GW plan redistributed)
5 GW overall plan under redesign; first phase Stargate UAE cited as $30B / 1 GW cluster with first 200 MW due in 2026
- Counterparty
- OpenAI; Oracle; Nvidia; SoftBank; Cisco (U.S. partners cited)
- Where
- United Arab Emirates (originally single ~10 sq mi Abu Dhabi campus near Al Dhafra; now likely multi-site network)
- Amount
- $30B
- MW
- 200
- GPUs
- —
Reuters exclusive Sep 11, 2026: after Iranian attacks, UAE revising 5 GW AI campus from one Abu Dhabi mega-campus toward a distributed network with hardening (air defenses, possible underground). G42 says work progressing as planned and specifics under continuous review. amountUsd/mw fields reflect the cited first-phase Stargate UAE cluster ($30B / 1 GW / first 200 MW this year), not a newly signed lease. Not a new offtake; redesign of an existing buildout.
Nvidia
Sep 10, 2026
Announced · AI factory / data center capacity partnerships (DSX platform)
Up to 2 GW of AI-related capacity by 2027 (partners' sites; Australia's current computing capacity cited at 1.6 GW)
- Counterparty
- Firmus, Sharon AI, IREN, Megaport, ResetData, CDC, NEXTDC, AirTrunk
- Where
- Australia
- Amount
- —
- MW
- —
- GPUs
- —
Reuters Sep 10, 2026: Nvidia working with eight Australian cloud/data-centre firms targeting up to 2 GW AI capacity by 2027 using Nvidia DSX. Partner list also reported by The Next Web. No capital commitment, per-site timetable, named end-customer offtake, or generation source disclosed. Not a single lease; ecosystem buildout target.
Fluidstack
Sep 10, 2026
Under construction · AI data center campus (phase-one site work / worksite permit)
$4B phase one on >1,100 acres; critical IT load and anchor tenant not disclosed; phase-one completion targeted mid-2028
- Counterparty
- Cameron County (worksite permit); AEP Texas (transmission); East Rio Hondo Water Supply Corporation (water); anchor tenant not disclosed
- Where
- Unincorporated Cameron County, Texas, US (near Rio Hondo / Valley International Airport)
- Amount
- $4B
- MW
- —
- GPUs
- —
Cameron County worksite permit issued Sep 10, 2026 (clearing/grading/utilities only; building permits still required). Fluidstack and local coverage describe a $4B first phase on more than 1,100 acres with mid-2028 phase-one target and closed-loop cooling. Do not invent MW: Fluidstack has not published critical IT load. No lease, Google backstop, or named offtaker disclosed for this campus.
Google
Sep 9, 2026
Announced · AI/data center infrastructure investment + nuclear/wind power offtake
At least €13B ($15.1B) for 2027–2028; 22-year PPA for up to 50% of Loviisa nuclear output; 629 MW new-to-grid onshore wind supported; 94 MW battery near Kajaani (late 2027). Campus IT load MW undisclosed.
- Counterparty
- Fortum (Loviisa nuclear PPA); Valorem and Suomen Hyötytuuli (onshore wind PPAs); Fingrid partnership
- Where
- Finland (Hamina expansion; new sites in Kajaani, Muhos, Vaala; Loviisa nuclear)
- Amount
- $15.1B
- MW
- —
- GPUs
- —
Google Sep 9, 2026 press + Reuters: largest single Google investment in Europe. Three new northern data centers plus Hamina expansion. First Google nuclear PPA outside the U.S. Fortum: PPA supports Loviisa life extension through 2050. MoU with Fortum to explore new nuclear/flexibility. Wind total 629 MW is Google-supported new-to-grid capacity, not data-center IT load. Battery is 94 MW grid flexibility near Kajaani.
OpenAI
Sep 8, 2026
Announced · AI compute offtake / anchor customer (multi-year)
Dedicated capacity from two Malaysian AI Factory sites; Firmus total contracted capacity across all customers now >900 MW (OpenAI share undisclosed)
- Counterparty
- Firmus (Nvidia-backed AI infrastructure)
- Where
- Malaysia (two Firmus AI Factory sites)
- Amount
- —
- MW
- —
- GPUs
- —
Firmus + OpenAI multi-year partnership Sep 8, 2026: OpenAI becomes anchor customer contracting dedicated AI compute from two Firmus AI Factory sites in Malaysia, with Vera Rubin / NVIDIA DSX planned. Firmus said the deal lifted its total contracted capacity across all customers to more than 900 MW; it declined to disclose OpenAI contract value or OpenAI-specific MW. Five Firmus sites (incl. Malaysia) are under development; two operational in Australia and Singapore. Also covered on Firmus newsroom.
HyperVault (TCS subsidiary)
Sep 5, 2026
Announced · AI data center campus (build / capacity announcement)
Up to 1 GW AI campus; 264 acres; up to Rs 70,000 crore (~$7.41B) investment
- Counterparty
- Government of Telangana; TPG (strategic partner); other unnamed partners
- Where
- Hyderabad / Future City, Telangana, India
- Amount
- $7.4B
- MW
- —
- GPUs
- —
Reuters Sep 5, 2026 (and TCS HyperVault press): HyperVault + partners to invest up to 700 billion rupees (~$7.41B) for a phased up-to-1GW AI campus on 264 acres in Hyderabad. Aimed at AI companies and hyperscalers; no named anchor tenant or signed PPA in the announcement. CM set a June 2, 2028 inauguration target (state Formation Day).
Jane Street
Sep 3, 2026
Announced · AI cloud compute offtake (GPU clusters)
~$13B five-year cloud/GPU commitment for training and inference; MW and GPU counts not disclosed
- Counterparty
- Crusoe
- Where
- Crusoe cloud (sites undisclosed in reporting)
- Amount
- $13B
- MW
- —
- GPUs
- —
Bloomberg Sep 3, 2026 (people familiar); neither company confirmed on the record. Featured in Sep 4 AI Today morning brief. Jane Street also previously committed ~$6B to CoreWeave (not double-counted here).
Figure
Sep 3, 2026
Announced · AI cloud compute offtake / preferred-provider partnership
Initial $3.5B compute commitment; up to 100,000 Nvidia Vera Rubin GPUs; initial deployment targeted H2 2027; intent to scale past $6B
- Counterparty
- Nscale (UK neocloud); Nvidia Vera Rubin platform
- Where
- Barstow, Texas, US
- Amount
- $3.5B
- MW
- —
- GPUs
- 100,000
Joint company announcements Sep 3, 2026 (Figure + Nscale). GPU figure is a ceiling ('up to 100,000'); MW not stated. Nscale also takes an undisclosed stake in Figure and becomes preferred compute provider.
Dell Technologies
Sep 2, 2026
Announced · AI server capacity reservation / backlog
$95B AI backlog; $60.9B AI server orders in fiscal Q2
- Counterparty
- AI server customers (6,500+ AI customers cited)
- Where
- Global (Round Rock, Texas HQ)
- Amount
- $95B
- MW
- —
- GPUs
- —
Earnings print, not a single bilateral lease: record $60.9B AI server orders in quarter ended July 31; $16.4B AI-optimized server revenue; exited with $95B AI backlog. Labeled as capacity reservation / server backlog, not MW or site power.
Anthropic
Sep 1, 2026
Announced · Data center / power lease
~350 MW Texas campus; $35B cloud-computing commitment
- Counterparty
- Lambda (Nvidia-backed); Hut 8 developing campus; Nvidia reportedly holds lease
- Where
- Nueces County, Texas, US
- Amount
- $35B
- MW
- 350
- GPUs
- —
Reuters (source) and WSJ first report: Anthropic signed a $35B cloud deal with Lambda for a Hut 8 Texas DC at about 350 MW; WSJ said Nvidia would hold the lease. Parties did not immediately comment.
Emerald AI
Aug 28, 2026
Under construction · Power-flexible AI factory / data center
Nearly 100 MW Vera Rubin power-flexible AI factory
- Counterparty
- Digital Realty; Nvidia; tested with EPRI, Dominion, PJM
- Where
- Manassas, Virginia, US
- Amount
- —
- MW
- 100
- GPUs
- —
Company announcement via VentureBeat (Aug 25 round context; Closing Time Aug 28): Manassas project with Digital Realty and Nvidia, nearly 100 MW, slated later this year. Equity round ($150M Series A) is separate; this row is the site/power project.
Microsoft
Aug 28, 2026
Announced · GPU lease (neocloud financing)
~$1B short-dated private debt to buy Nvidia GPUs Microsoft will lease
- Counterparty
- Lambda (Nvidia-backed); JPMorgan-arranged debt
- Where
- Undisclosed
- Amount
- $1B
- MW
- —
- GPUs
- —
Bloomberg / TechCrunch: Lambda raised about $1B short-dated private debt arranged by JPMorgan to buy Nvidia GPUs that Microsoft will lease; separate ~$926M term loan that week. GPU count not printed.
Amazon Web Services
Aug 27, 2026
Announced · GPU capacity expansion
2 million Nvidia GPUs across 2027–2028 (on top of 1M agreed March)
- Counterparty
- Nvidia
- Where
- AWS regions (undisclosed)
- Amount
- —
- MW
- —
- GPUs
- 2,000,000
TechCrunch on Nvidia earnings call: AWS will add two million Nvidia GPUs across 2027 and 2028, atop one million agreed in March. Terms undisclosed.
Anthropic
Aug 26, 2026
Announced · AI cloud compute rental
~460 MW; Nvidia Vera Rubin; ~6-year commitment; start ~end-2027
- Counterparty
- Nscale (UK neocloud)
- Where
- West Virginia, US
- Amount
- $45B
- MW
- 460
- GPUs
- —
Bloomberg first, CNBC confirmed: ~$45B to rent capacity at Nscale’s flagship West Virginia development; ~460 MW; Vera Rubin hardware; people said six years and end-of-2027 start.
AM Intelligence
Aug 26, 2026
Announced · GPU systems order / gigawatt compute plan
9,000 Nvidia Vera Rubin systems; $8B plan for ~1 GW compute
- Counterparty
- Nvidia (systems order); Greenko-backed
- Where
- Southern India
- Amount
- $8B
- MW
- —
- GPUs
- 9,000
Bloomberg: Greenko-backed AM Intelligence placed a binding order for 9,000 Vera Rubin systems under an $8B plan to stand up a gigawatt of compute; servers slated next year in southern India.
Nvidia
Aug 24, 2026
Announced · Power / site investment (Stargate campus)
Stargate campus power landlord stake; dollar size only described as billions
- Counterparty
- Lancium (Stargate power developer); OpenAI explored stake then walked
- Where
- Abilene, Texas, US
- Amount
- —
- MW
- —
- GPUs
- —
The Information: OpenAI explored investing in or acquiring Lancium (power developer behind Stargate in Abilene) last quarter before Nvidia put billions into the same firm. Exact check size beyond 'billions' not printed.
Nvidia
Aug 22, 2026
Announced · Power-and-site developer partnership / minority stake
Site, power, cooling, compute decisions via Nvidia DSX; stake size undisclosed
- Counterparty
- Cloverleaf Infrastructure
- Where
- US (utilities ↔ data-center developers)
- Amount
- —
- MW
- —
- GPUs
- —
TechCrunch: Nvidia partners with Cloverleaf (2024 power-and-site developer that raised $300M that year) and takes a minority stake; size undisclosed (other reports: hundreds of millions). Extends Nvidia’s infrastructure bets after $1.5B SB Energy stake tied to OpenAI’s Ohio campus.
Amazon Web Services
Aug 18, 2026
Under construction · Multi-campus data center investment / lease campuses
Three campuses; planned investment raised to $18B (from $12B in Feb); MW not disclosed in Amazon release
- Counterparty
- STACK Infrastructure (developer/owner cited in coverage); SWEPCO (power)
- Where
- Caddo & Bossier Parishes / Shreveport, Louisiana, US
- Amount
- $18B
- MW
- —
- GPUs
- —
Amazon Aug 18, 2026 update of Feb $12B plan: third Shreveport campus brings NW Louisiana planned investment to $18B. No IT-load MW in Amazon’s own release.
OpenAI
Aug 17, 2026
Under construction · Data center lease / AI factory campus (PORTS-Pike)
~8 GW-IT under 20-year lease; initial 4.25 IT-GW with Nvidia credit support; first ~800 MW targeted 2028
- Counterparty
- SB Energy (SoftBank-controlled); Nvidia (exclusive compute + credit support)
- Where
- Pike County, Ohio, US (PORTS-Pike / former Portsmouth site)
- Amount
- —
- MW
- —
- GPUs
- —
OpenAI Aug 17, 2026: ~8 GW-IT at PORTS-Pike; SB Energy builds/owns/operates under 20-year lease; Nvidia exclusive AI compute, $1.5B SB Energy investment, credit support on initial 4.25 IT-GW (SEC residual-value guarantee capped at $105B cited elsewhere — not campus lease rent). First 800 MW expected 2028. Later Daily/CNBC covered SB Energy S-1 dependency on OpenAI as tenant.
CoreWeave
Aug 4, 2026
Announced · Data center expansion / contracted IT power
360 MW contracted IT power across three facilities; expected online 2028
- Counterparty
- Indonesia facilities (own-and-operate; three sites)
- Where
- Indonesia (Asia-Pacific; first CoreWeave APAC DCs)
- Amount
- —
- MW
- 360
- GPUs
- —
Reuters / CoreWeave Aug 4, 2026: three Indonesia facilities totaling 360 MW contracted IT power, own-and-operate, targeted 2028. Capex not disclosed in the Reuters brief.
Brookfield (developer/operator selected by DOE)
Jul 29, 2026
Announced · AI/HPC campus on former enrichment site + dedicated power
Up to ~1.8 GW utility / >1.2 GW compute stated; $100B investment figure in coalition release
- Counterparty
- NextEra Energy (dedicated generation); U.S. DOE Paducah Site
- Where
- McCracken County, Kentucky, US (Paducah American Energy Hub)
- Amount
- $100B
- MW
- 1200
- GPUs
- —
Coalition Jul 29, 2026 via Axis: Brookfield+NextEra on DOE Paducah Site. DOE Aug 4 account differs on completion year (2031 vs 2032) and phrasing of capacity. $100B is stated investment, not a signed tenant offtake. PSC approval still required for power service agreement.
Meta Platforms
Jul 28, 2026
Under construction · Data center JV / lease of entire campus
1 GW compute capacity campus; ~$14B development costs; Meta leases entire campus; online beginning ~2028
- Counterparty
- BlackRock-managed funds (80% venture interest); Meta 20%
- Where
- El Paso, Texas, US
- Amount
- $14B
- MW
- —
- GPUs
- —
Meta/BlackRock Jul 28, 2026: 80/20 venture; ~$14B development costs; 1 GW compute; Meta sole initial occupant via lease. RVG aggregate ~$13B cited in Meta release.
OpenAI
Jul 22, 2026
Announced · Self-build AI data center campus + power contract (Project Camellia)
3.2 GW contracted power phased 2028–2032; county framed ~$20B minimum investment
- Counterparty
- Georgia Power (power offtake); self-develop campus
- Where
- Effingham County, Georgia, US (Savannah Gateway Industrial Hub)
- Amount
- $20B
- MW
- —
- GPUs
- —
OpenAI Jul 22, 2026: designing/developing Camellia; 3.2 GW from Georgia Power phased 2028–2032. $20B is the county/incentive framing (Bloomberg cited >$30B at full build — not used as amountUsd). Acres (~1,400) from local coverage of four-building campus. Power figure is contracted utility delivery, not disclosed critical IT load.
Nvidia (reported tenant; Hut 8 named only as investment-grade)
Jul 20, 2026
Under construction · Data center lease (15-year phases; campus commercialization)
704 MW IT across two 352 MW leases; 1 GW utility campus; $19.6B base-term contract value
- Counterparty
- Hut 8 (Beacon Point campus)
- Where
- Nueces County, Texas, US (Beacon Point)
- Amount
- $19.6B
- MW
- 704
- GPUs
- —
Hut 8 Jul 20, 2026: second 15-year $9.8B / 352 MW lease doubles same IG tenant to 704 MW IT; campus base-term $19.6B (renewals could reach ~$50.2B). FT later named Nvidia as tenant; Hut 8 release did not name the counterparty. Related but distinct from Anthropic’s later Lambda cloud offtake on the same campus.
Meta Platforms (via Anviran LLC)
Jul 14, 2026
Announced · Data center lease (20-year NNN)
175 MW critical IT; ~$6.6B contracted revenue initial term (up to ~$11.6B with extensions); deliveries Q4 2027
- Counterparty
- CleanSpark (Sandersville campus)
- Where
- Sandersville, Georgia, US
- Amount
- $6.6B
- MW
- 175
- GPUs
- —
CleanSpark Jul 14, 2026 announced 20-year NNN lease with unnamed high-investment-grade tenant ($6.6B initial term; up to ~$11.6B with extensions; rent from ~Nov 30, 2027). Sep 17, 2026 disclosure in investor materials/SEC context: tenant Anviran LLC is a wholly owned Meta subsidiary; Meta guarantees rent and opex. Concurrent $2.227B senior secured notes plan (CSDC Finance I) to fund remaining construction — offering not closed. LOI/exclusivity over CleanSpark Texas portfolio (up to 885 MW) noted but not counted as a separate closed lease. Meta reveal coverage: https://thedeepdive.ca/cleanspark-reveals-meta-behind-6-6-billion-ai-lease-requires-2-23-billion-financing/
Meta Platforms
Jul 13, 2026
Under construction · Hyperscaler AI campus expansion (self-build / JV)
Expanded to 5 GW compute capacity; >$50B regional investment; ~2 GW targeted by 2030, full ~2032
- Counterparty
- Blue Owl / Beignet Investors JV; Entergy Louisiana (power)
- Where
- Richland Parish, Louisiana, US (Hyperion)
- Amount
- $50B
- MW
- —
- GPUs
- —
CNBC on Meta Jul 13, 2026: Hyperion raised from prior ~2 GW / $27B JV framing to 5 GW and >$50B. Meta did not separate critical IT load from site power in the announcement; amount is investment figure, not a bilateral lease rent.
Meta Platforms
Jul 8, 2026
Under construction · AI-optimized data center campus (self-build)
1 GW AI-optimized campus; >CAD $13B investment (USD equivalent not converted here)
- Counterparty
- Self-build; Alberta grid partners (Greenlight LP, AltaLink, Capital Power, AESO cited)
- Where
- Sturgeon County, Alberta, Canada
- Amount
- —
- MW
- —
- GPUs
- —
Meta Jul 8, 2026: groundbreaking on 1GW AI-optimized DC in Sturgeon County, Alberta — first Canada site; >CAD $13B investment. amountUsd null (CAD not converted). IT vs gross capacity not separated.
Anthropic
Jul 6, 2026
Announced · Data center lease (20-year)
~401 MW critical IT load; phased H2 2027 → full early 2028; ~$19B contracted lease revenue
- Counterparty
- TeraWulf (Raylan Data LLC)
- Where
- Hawesville / Hancock County, Kentucky, US (Justified Data campus)
- Amount
- $19B
- MW
- 401
- GPUs
- —
TeraWulf Jul 6, 2026 press / 8-K: 20-year lease for ~401 MW critical IT; ~$19B contracted revenue over initial term; IG credit support expected. Separate Abernathy JV sale to Fluidstack-led group is not this row.
Microsoft
Jun 23, 2026
Live · AI data center campus (Fairwater) — first facility live
First Fairwater facility fully operational; MW undisclosed; second facility targeted 2028; Microsoft cites ~$4.7B statewide WI hyperscale construction spend 2024–2028 (not used as deal amount)
- Counterparty
- Self-build (Village of Mount Pleasant / Racine County)
- Where
- Mount Pleasant, Wisconsin, US
- Amount
- —
- MW
- —
- GPUs
- —
Microsoft Jun 23, 2026: first Mount Pleasant Fairwater DC complete/operational after April startup. No IT-load MW in release. Dollar figure in coverage is statewide construction-spend estimate, so amountUsd is null. Acres (315) from campus plan coverage of original site.
Google
Jun 15, 2026
Under construction · Data center campus expansion
$1.5B investment across 2026–2027; site MW undisclosed (300 MW cited as contracted regional generation, not campus IT load)
- Counterparty
- Self-build expansion; TVA region power partners
- Where
- Jackson County, Alabama, US
- Amount
- $1.5B
- MW
- —
- GPUs
- —
Google Jun 15, 2026: $1.5B investment across 2026–2027 to expand Jackson County campus (former Widows Creek coal plant). Critical IT load not disclosed; >300 MW cited as contracted regional generation for TVA area, not campus IT load.
Anthropic
May 3, 2026
Live · Cloud / GPU offtake (Colossus I & II)
~$1.25B/month through May 2029 (~$15B/yr); ~325,000 Nvidia GPUs cited in amended S-1 coverage
- Counterparty
- SpaceX (xAI Colossus campuses)
- Where
- Memphis, Tennessee, US (Colossus / Colossus II)
- Amount
- —
- MW
- —
- GPUs
- 325,000
SpaceX S-1 (May 2026) disclosed Cloud Services Agreements with Anthropic for Colossus/Colossus II at $1.25B/month through May 2029; either party may terminate on 90 days’ notice after ramp. GPU count ~325k from amended S-1 coverage; MW not reliably stated as a single leased figure. amountUsd left null (term depends on duration/termination).
Meta Platforms
Apr 21, 2026
Under construction · AI-optimized data center campus (self-build)
AI-optimized campus; >$1B regional investment; MW not stated in release
- Counterparty
- Self-build
- Where
- Tulsa, Oklahoma, US
- Amount
- $1B
- MW
- —
- GPUs
- —
Meta Apr 21, 2026 (page also shows Apr 20): first Oklahoma AI-optimized DC; >$1B regional investment. Campus MW not disclosed.
Anthropic
Apr 20, 2026
Announced · Cloud compute offtake / capacity envelope
Up to 5 GW new capacity; >$100B AWS tech spend over 10 years; ~1 GW Trainium2+3 targeted by end-2026
- Counterparty
- Amazon Web Services (Trainium / Graviton)
- Where
- AWS regions (incl. Project Rainier / Indiana cited in secondary coverage; sites not fully enumerated in Anthropic release)
- Amount
- $100B
- MW
- —
- GPUs
- —
Anthropic Apr 20, 2026 primary: up to 5 GW and >$100B over ten years on AWS technologies (Trainium2–4, Graviton). Not a named single-site lease; Amazon equity ($5B + up to $20B more) is separate from the offtake spend figure used in amountUsd.
Meta Platforms
Apr 9, 2026
Announced · AI cloud capacity offtake (multi-year)
~$21B expanded agreement through Dec 2032; Vera Rubin deployments; prior relationship brings combined ~$35B cited in coverage
- Counterparty
- CoreWeave
- Where
- Multiple CoreWeave locations (undisclosed)
- Amount
- $21B
- MW
- —
- GPUs
- —
CoreWeave Apr 9, 2026: expanded long-term Meta agreement ~$21B through Dec 2032 for dedicated AI cloud capacity across multiple sites, including early Vera Rubin. MW/GPU counts not in the company release.
Amazon Web Services
Mar 18, 2026
Announced · GPU capacity expansion / reservation
>1 million Nvidia GPUs starting 2026 (Blackwell/Rubin architectures cited)
- Counterparty
- Nvidia
- Where
- AWS regions (global)
- Amount
- —
- MW
- —
- GPUs
- 1,000,000
AWS blog at Nvidia GTC 2026: deploy more than 1M Nvidia GPUs across AWS regions starting 2026. announced date set to mid-March GTC window (exact keynote day not pinned in the blog slug). Aug 2026 +2M expansion tracked separately as aws-nvidia-gpus-2027-2028.
Meta Platforms
Feb 11, 2026
Under construction · AI / hyperscale data center campus (self-build)
Designed for 1 GW capacity; >$10B investment cited
- Counterparty
- Self-build
- Where
- Lebanon, Indiana, US (Boone County)
- Amount
- $10B
- MW
- —
- GPUs
- —
Meta Feb 11, 2026: groundbreaking on 1GW Lebanon, Indiana campus; investment over $10B. IT vs gross capacity not separated.
| Counterparty | What | Where | Amount | Status | Source | |||
|---|---|---|---|---|---|---|---|---|
| Sep 21, 2026 | New Era Energy & Digital (TCDC PowerCo) | Luminant ET Services (Vistra affiliate) | 20-year power purchase agreement (Phase 1) | Texas Critical Data Center, Odessa / Permian Basin, Texas, US | Minimum 200 MW up to 207 MW for Phase 1; power from Vistra's adjacent 1,180 MW Odessa gas plant; expected available Q3 2027; campus planned to scale toward 1.4 GW over time (493-acre site) Company PR + MarketWatch/RTT Sep 21, 2026. mw set to the contracted maximum (207); minimum is 200. Vistra also gets a 5% non-voting interest in the powered project portion plus ROFR/ROFO on future development. amountUsd null (not disclosed). Full-campus 1.4 GW is planned scale, not contracted Phase 1. | — | Announced | Link |
| Sep 21, 2026 | Sharon AI | GreenSquare | Long-term AI data center customer / capacity agreement (SYD1 Stage 1) | SYD1 campus, Norwest Business Park, Western Sydney, NSW, Australia | ~8,200 NVIDIA Blackwell Ultra GPUs (HGX B300) expected; initial operations targeted Q4 2026; SYD1 planned as 100 MW+ campus; Stage 1 reuses existing DC building GreenSquare/techpartner/w.media Sep 21, 2026. Financial terms and contracted MW not disclosed — mw/amountUsd left null. Campus pipeline cited as 100 MW+ at SYD1 and >1 GW broader GreenSquare portfolio; those are campus/pipeline figures, not Sharon's contracted allotment. | — | Announced | Link |
| Sep 21, 2026 | West Texas data center operator (unnamed; contracted with investment-grade hyperscaler; GPU designer as lease guarantor) | Kodiak Gas Services | Six-year behind-the-meter baseload power supply (incl. balance of plant) | West Texas, US | 76 MW behind-the-meter; ~40 reciprocating natural-gas generation units; deploy Q4 2026 scaling into Q1 2027; revenue expected from Q1 2027 Kodiak IR PR Sep 21, 2026. Operator, hyperscaler, and GPU-designer guarantor not named. amountUsd null. Kodiak's second long-term primary-power contract to a data center. | — | Announced | Link |
| Sep 21, 2026 | Georgia Power | Nuclear uprate subscription (NU-1 tariff / ZECs) | Plants Vogtle and Hatch, Georgia, US | ~96 MW new nuclear capacity via EPUs on Georgia Power’s owned share of Vogtle and Hatch; ~$900M projected customer benefits over unit life (not Google payment) Georgia Power press release Sep 21, 2026 (PSC filings Docket 44280, 56002). Subject to Georgia PSC approval. Google subscribes to new NU-1 tariff and receives Zero-Emission Credits for the uprate output; structure protects non-participating customers from incremental uprate cost. Hatch 1&2 EPU still needs PSC approval; Vogtle 1&2 EPU was approved in 2025 IRP. NRC license amendments still required. $900M figure is projected customer benefits, not disclosed Google spend — amountUsd left null. | — | Announced | Link | |
| Sep 18, 2026 | Amazon Web Services | PPC (Public Power Corporation of Greece / ΔΕΗ) | Data center lease + renewable PPAs (binding MoU) | Agios Dimitrios (Kozani / Western Macedonia), Greece | 300 MW first phase (four 75 MW units); explore up to 1 GW; 15-year lease once built; PPC ~€1.2B first-phase build Binding MoU (regulated Athens Exchange disclosure also filed). AWS leases and runs IT; PPC owns buildings/land/energy infra and supplies renewable PPAs (>10 years). Expansion to 1 GW optional, needs further definitive agreements. First 300 MW targeted operational by end-2028; construction could begin end-2026. €1.2B is PPC first-phase capex, not lease contract value — amountUsd left null. | — | Announced | Link |
| Sep 17, 2026 | Oracle | RWE Americas (Panther Creek I, II, III wind) | Virtual power purchase agreement (VPPA) | West Texas (Sterling, Howard, Glasscock counties), US — ERCOT; supports Oracle data centers | 433 MW from existing Panther Creek I–III wind farms; part of Oracle’s broader >1.7 GW Texas carbon-free portfolio RWE press release Sep 17, 2026. VPPA supplies Texas grid in support of Oracle data-center operations; Panther Creek farms previously repowered. Oracle cites goal to match 100% of AI data-center electricity with carbon-free power by 2035. amountUsd not disclosed. | — | Announced | Link |
| Sep 17, 2026 | Oracle | ENGIE North America | Renewable energy supply agreements (wind / ERCOT) | Texas, US (ERCOT); supports Oracle Texas / AI data-center operations | Up to 568 MW renewable electricity from ENGIE wind resources serving ERCOT; part of Oracle’s broader >1.7 GW Texas carbon-free portfolio ENGIE North America PR via PR Newswire Sep 17, 2026. Portfolio of wind resources; more than 500 MW / up to 568 MW. Dollar value and contract term not disclosed. Clearway also named in secondary coverage of the >1.7 GW Oracle Texas portfolio but no Clearway-primary MW disclosure found for a separate row. | — | Announced | Link |
| Sep 16, 2026 | Anthropic | Zerra DC (Singapore-based developer) | Data center lease (first Australia site; inference capacity) | Western Downs Digital Park near Dalby, Queensland, Australia (~250 km from Brisbane) | Planned 2.16 GW campus; ~A$32 billion development; online from 2027 (subject to FIRB) First Anthropic Australia data-centre lease per Reuters (sources). Campus planned by Zerra DC; Anthropic/Zerra declined comment. Subject to Foreign Investment Review Board approval. ABC/Brisbane Times cite ~A$32B campus cost; Reuters cites 2.16 GW total planned capacity. Inference use, not training. Do not treat A$ as USD. | — | Announced | Link |
| Sep 15, 2026 | Perplexity | Crusoe | Multi-year AI cloud compute offtake (training + managed inference) | Crusoe Cloud (sites undisclosed in reporting) | Dedicated NVIDIA GB300 NVL72 clusters for training; production via Crusoe Managed Inference; MW, GPU count, and dollar value not disclosed Bloomberg Sep 15, 2026 + Crusoe GlobeNewswire same day. Multi-year partnership for full model lifecycle on Crusoe Cloud; Crusoe also adopts Perplexity Enterprise for ~1,800 employees (software side, not capacity). Separate from Jane Street × Crusoe offtake already on tracker. | — | Announced | Link |
| Sep 14, 2026 | Bitdeer AI | Unnamed data-center services landlord (same Johor Bahru campus as A201) | 10-year data center services agreement (AI Cloud facility lease) | Johor Bahru, Malaysia (existing Bitdeer AI campus with A201) | 65.1 MW A202 IT load; energization targeted Q3 2027; with 21.7 MW A201 campus totals 86.8 MW Bitdeer AI company PR via GlobeNewswire Sep 14, 2026 (republished on FinancialContent). Largest single SEA capacity add; liquid-cooled rack-scale NVIDIA GB300 NVL72 / Vera Rubin capable. Facility-level DC lease only — no named end-customer offtake for A202 disclosed at announcement. amountUsd left null (pipeline figure is company-wide, not this lease). | — | Announced | Link |
| Sep 14, 2026 | Bell Canada (Bell AI Fabric) | Government of Saskatchewan | AI data center campus expansion (non-binding MOU) | Near Regina (R.M. of Sherwood), Saskatchewan, Canada | Pathway to 1.2 GW hub: existing ~300 MW under construction on provincial grid + up to 900 MW additional under Bring Your Own Power (partner gas generation); >$50B / ~$52.5B total capital figure cited including tenant compute and power gen Saskatchewan government news release Sep 14, 2026 (also Bell / CNW coverage Sep 15). Non-binding MOU — expansion subject to customer commitments, commercial agreements, permits, and environmental approvals. amountUsd is the reported ~$52.5B / >$50B prospective total capital (campus + tenant compute + power), not a signed lease NPV. 300 MW phase already under construction; this row captures the expansion-to-1.2 GW announcement. | $52.5B | Announced | Link |
| Sep 13, 2026 | Anthropic | RUM Group (ex-Rumble; Northern Data / Quake AI) | GPU services / compute lease (six-year, three tranches) | Maysville, Georgia, US (Banks/Jackson counties) | Up to $13.7B over six years; site planned ~120 MW expandable to ~180 MW; ops targeted early 2027 / Q1 2027 The Information (Sep 13, 2026) identified Anthropic as the previously unnamed customer in RUM Group's Aug 24, 2026 8-K; neither Anthropic nor RUM had publicly confirmed at TECHi's publish time. Commercial agreement signed Aug 23 for GPU access/services at Maysville in three ~equal tranches (~$13.7B total); third tranche contingent on customer approval of delivery date. Customer also gets warrant for up to ~50.8M RUM Class A shares at $0.01. RUM disclosed it does not yet have financing to build the facility/buy GPUs. MW/acres from Northern Data's Dec 2024 Maysville campus plan (120 MW near-term, expand to 180 MW, 63 acres) as cited by DCD; do not invent GPU count. | $13.7B | Under construction | Link |
| Sep 11, 2026 | G42 (UAE AI campus / Stargate UAE) | OpenAI; Oracle; Nvidia; SoftBank; Cisco (U.S. partners cited) | AI data center campus redesign (5 GW plan redistributed) | United Arab Emirates (originally single ~10 sq mi Abu Dhabi campus near Al Dhafra; now likely multi-site network) | 5 GW overall plan under redesign; first phase Stargate UAE cited as $30B / 1 GW cluster with first 200 MW due in 2026 Reuters exclusive Sep 11, 2026: after Iranian attacks, UAE revising 5 GW AI campus from one Abu Dhabi mega-campus toward a distributed network with hardening (air defenses, possible underground). G42 says work progressing as planned and specifics under continuous review. amountUsd/mw fields reflect the cited first-phase Stargate UAE cluster ($30B / 1 GW / first 200 MW this year), not a newly signed lease. Not a new offtake; redesign of an existing buildout. | $30B | Under construction | Link |
| Sep 10, 2026 | Nvidia | Firmus, Sharon AI, IREN, Megaport, ResetData, CDC, NEXTDC, AirTrunk | AI factory / data center capacity partnerships (DSX platform) | Australia | Up to 2 GW of AI-related capacity by 2027 (partners' sites; Australia's current computing capacity cited at 1.6 GW) Reuters Sep 10, 2026: Nvidia working with eight Australian cloud/data-centre firms targeting up to 2 GW AI capacity by 2027 using Nvidia DSX. Partner list also reported by The Next Web. No capital commitment, per-site timetable, named end-customer offtake, or generation source disclosed. Not a single lease; ecosystem buildout target. | — | Announced | Link |
| Sep 10, 2026 | Fluidstack | Cameron County (worksite permit); AEP Texas (transmission); East Rio Hondo Water Supply Corporation (water); anchor tenant not disclosed | AI data center campus (phase-one site work / worksite permit) | Unincorporated Cameron County, Texas, US (near Rio Hondo / Valley International Airport) | $4B phase one on >1,100 acres; critical IT load and anchor tenant not disclosed; phase-one completion targeted mid-2028 Cameron County worksite permit issued Sep 10, 2026 (clearing/grading/utilities only; building permits still required). Fluidstack and local coverage describe a $4B first phase on more than 1,100 acres with mid-2028 phase-one target and closed-loop cooling. Do not invent MW: Fluidstack has not published critical IT load. No lease, Google backstop, or named offtaker disclosed for this campus. | $4B | Under construction | Link |
| Sep 9, 2026 | Fortum (Loviisa nuclear PPA); Valorem and Suomen Hyötytuuli (onshore wind PPAs); Fingrid partnership | AI/data center infrastructure investment + nuclear/wind power offtake | Finland (Hamina expansion; new sites in Kajaani, Muhos, Vaala; Loviisa nuclear) | At least €13B ($15.1B) for 2027–2028; 22-year PPA for up to 50% of Loviisa nuclear output; 629 MW new-to-grid onshore wind supported; 94 MW battery near Kajaani (late 2027). Campus IT load MW undisclosed. Google Sep 9, 2026 press + Reuters: largest single Google investment in Europe. Three new northern data centers plus Hamina expansion. First Google nuclear PPA outside the U.S. Fortum: PPA supports Loviisa life extension through 2050. MoU with Fortum to explore new nuclear/flexibility. Wind total 629 MW is Google-supported new-to-grid capacity, not data-center IT load. Battery is 94 MW grid flexibility near Kajaani. | $15.1B | Announced | Link | |
| Sep 8, 2026 | OpenAI | Firmus (Nvidia-backed AI infrastructure) | AI compute offtake / anchor customer (multi-year) | Malaysia (two Firmus AI Factory sites) | Dedicated capacity from two Malaysian AI Factory sites; Firmus total contracted capacity across all customers now >900 MW (OpenAI share undisclosed) Firmus + OpenAI multi-year partnership Sep 8, 2026: OpenAI becomes anchor customer contracting dedicated AI compute from two Firmus AI Factory sites in Malaysia, with Vera Rubin / NVIDIA DSX planned. Firmus said the deal lifted its total contracted capacity across all customers to more than 900 MW; it declined to disclose OpenAI contract value or OpenAI-specific MW. Five Firmus sites (incl. Malaysia) are under development; two operational in Australia and Singapore. Also covered on Firmus newsroom. | — | Announced | Link |
| Sep 5, 2026 | HyperVault (TCS subsidiary) | Government of Telangana; TPG (strategic partner); other unnamed partners | AI data center campus (build / capacity announcement) | Hyderabad / Future City, Telangana, India | Up to 1 GW AI campus; 264 acres; up to Rs 70,000 crore (~$7.41B) investment Reuters Sep 5, 2026 (and TCS HyperVault press): HyperVault + partners to invest up to 700 billion rupees (~$7.41B) for a phased up-to-1GW AI campus on 264 acres in Hyderabad. Aimed at AI companies and hyperscalers; no named anchor tenant or signed PPA in the announcement. CM set a June 2, 2028 inauguration target (state Formation Day). | $7.4B | Announced | Link |
| Sep 3, 2026 | Jane Street | Crusoe | AI cloud compute offtake (GPU clusters) | Crusoe cloud (sites undisclosed in reporting) | ~$13B five-year cloud/GPU commitment for training and inference; MW and GPU counts not disclosed Bloomberg Sep 3, 2026 (people familiar); neither company confirmed on the record. Featured in Sep 4 AI Today morning brief. Jane Street also previously committed ~$6B to CoreWeave (not double-counted here). | $13B | Announced | Link |
| Sep 3, 2026 | Figure | Nscale (UK neocloud); Nvidia Vera Rubin platform | AI cloud compute offtake / preferred-provider partnership | Barstow, Texas, US | Initial $3.5B compute commitment; up to 100,000 Nvidia Vera Rubin GPUs; initial deployment targeted H2 2027; intent to scale past $6B Joint company announcements Sep 3, 2026 (Figure + Nscale). GPU figure is a ceiling ('up to 100,000'); MW not stated. Nscale also takes an undisclosed stake in Figure and becomes preferred compute provider. | $3.5B | Announced | Link |
| Sep 2, 2026 | Dell Technologies | AI server customers (6,500+ AI customers cited) | AI server capacity reservation / backlog | Global (Round Rock, Texas HQ) | $95B AI backlog; $60.9B AI server orders in fiscal Q2 Earnings print, not a single bilateral lease: record $60.9B AI server orders in quarter ended July 31; $16.4B AI-optimized server revenue; exited with $95B AI backlog. Labeled as capacity reservation / server backlog, not MW or site power. | $95B | Announced | Link |
| Sep 1, 2026 | Anthropic | Lambda (Nvidia-backed); Hut 8 developing campus; Nvidia reportedly holds lease | Data center / power lease | Nueces County, Texas, US | ~350 MW Texas campus; $35B cloud-computing commitment Reuters (source) and WSJ first report: Anthropic signed a $35B cloud deal with Lambda for a Hut 8 Texas DC at about 350 MW; WSJ said Nvidia would hold the lease. Parties did not immediately comment. | $35B | Announced | Link |
| Aug 28, 2026 | Emerald AI | Digital Realty; Nvidia; tested with EPRI, Dominion, PJM | Power-flexible AI factory / data center | Manassas, Virginia, US | Nearly 100 MW Vera Rubin power-flexible AI factory Company announcement via VentureBeat (Aug 25 round context; Closing Time Aug 28): Manassas project with Digital Realty and Nvidia, nearly 100 MW, slated later this year. Equity round ($150M Series A) is separate; this row is the site/power project. | — | Under construction | Link |
| Aug 28, 2026 | Microsoft | Lambda (Nvidia-backed); JPMorgan-arranged debt | GPU lease (neocloud financing) | Undisclosed | ~$1B short-dated private debt to buy Nvidia GPUs Microsoft will lease Bloomberg / TechCrunch: Lambda raised about $1B short-dated private debt arranged by JPMorgan to buy Nvidia GPUs that Microsoft will lease; separate ~$926M term loan that week. GPU count not printed. | $1B | Announced | Link |
| Aug 27, 2026 | Amazon Web Services | Nvidia | GPU capacity expansion | AWS regions (undisclosed) | 2 million Nvidia GPUs across 2027–2028 (on top of 1M agreed March) TechCrunch on Nvidia earnings call: AWS will add two million Nvidia GPUs across 2027 and 2028, atop one million agreed in March. Terms undisclosed. | — | Announced | Link |
| Aug 26, 2026 | Anthropic | Nscale (UK neocloud) | AI cloud compute rental | West Virginia, US | ~460 MW; Nvidia Vera Rubin; ~6-year commitment; start ~end-2027 Bloomberg first, CNBC confirmed: ~$45B to rent capacity at Nscale’s flagship West Virginia development; ~460 MW; Vera Rubin hardware; people said six years and end-of-2027 start. | $45B | Announced | Link |
| Aug 26, 2026 | AM Intelligence | Nvidia (systems order); Greenko-backed | GPU systems order / gigawatt compute plan | Southern India | 9,000 Nvidia Vera Rubin systems; $8B plan for ~1 GW compute Bloomberg: Greenko-backed AM Intelligence placed a binding order for 9,000 Vera Rubin systems under an $8B plan to stand up a gigawatt of compute; servers slated next year in southern India. | $8B | Announced | Link |
| Aug 24, 2026 | Nvidia | Lancium (Stargate power developer); OpenAI explored stake then walked | Power / site investment (Stargate campus) | Abilene, Texas, US | Stargate campus power landlord stake; dollar size only described as billions The Information: OpenAI explored investing in or acquiring Lancium (power developer behind Stargate in Abilene) last quarter before Nvidia put billions into the same firm. Exact check size beyond 'billions' not printed. | — | Announced | Link |
| Aug 22, 2026 | Nvidia | Cloverleaf Infrastructure | Power-and-site developer partnership / minority stake | US (utilities ↔ data-center developers) | Site, power, cooling, compute decisions via Nvidia DSX; stake size undisclosed TechCrunch: Nvidia partners with Cloverleaf (2024 power-and-site developer that raised $300M that year) and takes a minority stake; size undisclosed (other reports: hundreds of millions). Extends Nvidia’s infrastructure bets after $1.5B SB Energy stake tied to OpenAI’s Ohio campus. | — | Announced | Link |
| Aug 18, 2026 | Amazon Web Services | STACK Infrastructure (developer/owner cited in coverage); SWEPCO (power) | Multi-campus data center investment / lease campuses | Caddo & Bossier Parishes / Shreveport, Louisiana, US | Three campuses; planned investment raised to $18B (from $12B in Feb); MW not disclosed in Amazon release Amazon Aug 18, 2026 update of Feb $12B plan: third Shreveport campus brings NW Louisiana planned investment to $18B. No IT-load MW in Amazon’s own release. | $18B | Under construction | Link |
| Aug 17, 2026 | OpenAI | SB Energy (SoftBank-controlled); Nvidia (exclusive compute + credit support) | Data center lease / AI factory campus (PORTS-Pike) | Pike County, Ohio, US (PORTS-Pike / former Portsmouth site) | ~8 GW-IT under 20-year lease; initial 4.25 IT-GW with Nvidia credit support; first ~800 MW targeted 2028 OpenAI Aug 17, 2026: ~8 GW-IT at PORTS-Pike; SB Energy builds/owns/operates under 20-year lease; Nvidia exclusive AI compute, $1.5B SB Energy investment, credit support on initial 4.25 IT-GW (SEC residual-value guarantee capped at $105B cited elsewhere — not campus lease rent). First 800 MW expected 2028. Later Daily/CNBC covered SB Energy S-1 dependency on OpenAI as tenant. | — | Under construction | Link |
| Aug 4, 2026 | CoreWeave | Indonesia facilities (own-and-operate; three sites) | Data center expansion / contracted IT power | Indonesia (Asia-Pacific; first CoreWeave APAC DCs) | 360 MW contracted IT power across three facilities; expected online 2028 Reuters / CoreWeave Aug 4, 2026: three Indonesia facilities totaling 360 MW contracted IT power, own-and-operate, targeted 2028. Capex not disclosed in the Reuters brief. | — | Announced | Link |
| Jul 29, 2026 | Brookfield (developer/operator selected by DOE) | NextEra Energy (dedicated generation); U.S. DOE Paducah Site | AI/HPC campus on former enrichment site + dedicated power | McCracken County, Kentucky, US (Paducah American Energy Hub) | Up to ~1.8 GW utility / >1.2 GW compute stated; $100B investment figure in coalition release Coalition Jul 29, 2026 via Axis: Brookfield+NextEra on DOE Paducah Site. DOE Aug 4 account differs on completion year (2031 vs 2032) and phrasing of capacity. $100B is stated investment, not a signed tenant offtake. PSC approval still required for power service agreement. | $100B | Announced | Link |
| Jul 28, 2026 | Meta Platforms | BlackRock-managed funds (80% venture interest); Meta 20% | Data center JV / lease of entire campus | El Paso, Texas, US | 1 GW compute capacity campus; ~$14B development costs; Meta leases entire campus; online beginning ~2028 Meta/BlackRock Jul 28, 2026: 80/20 venture; ~$14B development costs; 1 GW compute; Meta sole initial occupant via lease. RVG aggregate ~$13B cited in Meta release. | $14B | Under construction | Link |
| Jul 22, 2026 | OpenAI | Georgia Power (power offtake); self-develop campus | Self-build AI data center campus + power contract (Project Camellia) | Effingham County, Georgia, US (Savannah Gateway Industrial Hub) | 3.2 GW contracted power phased 2028–2032; county framed ~$20B minimum investment OpenAI Jul 22, 2026: designing/developing Camellia; 3.2 GW from Georgia Power phased 2028–2032. $20B is the county/incentive framing (Bloomberg cited >$30B at full build — not used as amountUsd). Acres (~1,400) from local coverage of four-building campus. Power figure is contracted utility delivery, not disclosed critical IT load. | $20B | Announced | Link |
| Jul 20, 2026 | Nvidia (reported tenant; Hut 8 named only as investment-grade) | Hut 8 (Beacon Point campus) | Data center lease (15-year phases; campus commercialization) | Nueces County, Texas, US (Beacon Point) | 704 MW IT across two 352 MW leases; 1 GW utility campus; $19.6B base-term contract value Hut 8 Jul 20, 2026: second 15-year $9.8B / 352 MW lease doubles same IG tenant to 704 MW IT; campus base-term $19.6B (renewals could reach ~$50.2B). FT later named Nvidia as tenant; Hut 8 release did not name the counterparty. Related but distinct from Anthropic’s later Lambda cloud offtake on the same campus. | $19.6B | Under construction | Link |
| Jul 14, 2026 | Meta Platforms (via Anviran LLC) | CleanSpark (Sandersville campus) | Data center lease (20-year NNN) | Sandersville, Georgia, US | 175 MW critical IT; ~$6.6B contracted revenue initial term (up to ~$11.6B with extensions); deliveries Q4 2027 CleanSpark Jul 14, 2026 announced 20-year NNN lease with unnamed high-investment-grade tenant ($6.6B initial term; up to ~$11.6B with extensions; rent from ~Nov 30, 2027). Sep 17, 2026 disclosure in investor materials/SEC context: tenant Anviran LLC is a wholly owned Meta subsidiary; Meta guarantees rent and opex. Concurrent $2.227B senior secured notes plan (CSDC Finance I) to fund remaining construction — offering not closed. LOI/exclusivity over CleanSpark Texas portfolio (up to 885 MW) noted but not counted as a separate closed lease. Meta reveal coverage: https://thedeepdive.ca/cleanspark-reveals-meta-behind-6-6-billion-ai-lease-requires-2-23-billion-financing/ | $6.6B | Announced | Link |
| Jul 13, 2026 | Meta Platforms | Blue Owl / Beignet Investors JV; Entergy Louisiana (power) | Hyperscaler AI campus expansion (self-build / JV) | Richland Parish, Louisiana, US (Hyperion) | Expanded to 5 GW compute capacity; >$50B regional investment; ~2 GW targeted by 2030, full ~2032 CNBC on Meta Jul 13, 2026: Hyperion raised from prior ~2 GW / $27B JV framing to 5 GW and >$50B. Meta did not separate critical IT load from site power in the announcement; amount is investment figure, not a bilateral lease rent. | $50B | Under construction | Link |
| Jul 8, 2026 | Meta Platforms | Self-build; Alberta grid partners (Greenlight LP, AltaLink, Capital Power, AESO cited) | AI-optimized data center campus (self-build) | Sturgeon County, Alberta, Canada | 1 GW AI-optimized campus; >CAD $13B investment (USD equivalent not converted here) Meta Jul 8, 2026: groundbreaking on 1GW AI-optimized DC in Sturgeon County, Alberta — first Canada site; >CAD $13B investment. amountUsd null (CAD not converted). IT vs gross capacity not separated. | — | Under construction | Link |
| Jul 6, 2026 | Anthropic | TeraWulf (Raylan Data LLC) | Data center lease (20-year) | Hawesville / Hancock County, Kentucky, US (Justified Data campus) | ~401 MW critical IT load; phased H2 2027 → full early 2028; ~$19B contracted lease revenue TeraWulf Jul 6, 2026 press / 8-K: 20-year lease for ~401 MW critical IT; ~$19B contracted revenue over initial term; IG credit support expected. Separate Abernathy JV sale to Fluidstack-led group is not this row. | $19B | Announced | Link |
| Jun 23, 2026 | Microsoft | Self-build (Village of Mount Pleasant / Racine County) | AI data center campus (Fairwater) — first facility live | Mount Pleasant, Wisconsin, US | First Fairwater facility fully operational; MW undisclosed; second facility targeted 2028; Microsoft cites ~$4.7B statewide WI hyperscale construction spend 2024–2028 (not used as deal amount) Microsoft Jun 23, 2026: first Mount Pleasant Fairwater DC complete/operational after April startup. No IT-load MW in release. Dollar figure in coverage is statewide construction-spend estimate, so amountUsd is null. Acres (315) from campus plan coverage of original site. | — | Live | Link |
| Jun 15, 2026 | Self-build expansion; TVA region power partners | Data center campus expansion | Jackson County, Alabama, US | $1.5B investment across 2026–2027; site MW undisclosed (300 MW cited as contracted regional generation, not campus IT load) Google Jun 15, 2026: $1.5B investment across 2026–2027 to expand Jackson County campus (former Widows Creek coal plant). Critical IT load not disclosed; >300 MW cited as contracted regional generation for TVA area, not campus IT load. | $1.5B | Under construction | Link | |
| May 3, 2026 | Anthropic | SpaceX (xAI Colossus campuses) | Cloud / GPU offtake (Colossus I & II) | Memphis, Tennessee, US (Colossus / Colossus II) | ~$1.25B/month through May 2029 (~$15B/yr); ~325,000 Nvidia GPUs cited in amended S-1 coverage SpaceX S-1 (May 2026) disclosed Cloud Services Agreements with Anthropic for Colossus/Colossus II at $1.25B/month through May 2029; either party may terminate on 90 days’ notice after ramp. GPU count ~325k from amended S-1 coverage; MW not reliably stated as a single leased figure. amountUsd left null (term depends on duration/termination). | — | Live | Link |
| Apr 21, 2026 | Meta Platforms | Self-build | AI-optimized data center campus (self-build) | Tulsa, Oklahoma, US | AI-optimized campus; >$1B regional investment; MW not stated in release Meta Apr 21, 2026 (page also shows Apr 20): first Oklahoma AI-optimized DC; >$1B regional investment. Campus MW not disclosed. | $1B | Under construction | Link |
| Apr 20, 2026 | Anthropic | Amazon Web Services (Trainium / Graviton) | Cloud compute offtake / capacity envelope | AWS regions (incl. Project Rainier / Indiana cited in secondary coverage; sites not fully enumerated in Anthropic release) | Up to 5 GW new capacity; >$100B AWS tech spend over 10 years; ~1 GW Trainium2+3 targeted by end-2026 Anthropic Apr 20, 2026 primary: up to 5 GW and >$100B over ten years on AWS technologies (Trainium2–4, Graviton). Not a named single-site lease; Amazon equity ($5B + up to $20B more) is separate from the offtake spend figure used in amountUsd. | $100B | Announced | Link |
| Apr 9, 2026 | Meta Platforms | CoreWeave | AI cloud capacity offtake (multi-year) | Multiple CoreWeave locations (undisclosed) | ~$21B expanded agreement through Dec 2032; Vera Rubin deployments; prior relationship brings combined ~$35B cited in coverage CoreWeave Apr 9, 2026: expanded long-term Meta agreement ~$21B through Dec 2032 for dedicated AI cloud capacity across multiple sites, including early Vera Rubin. MW/GPU counts not in the company release. | $21B | Announced | Link |
| Mar 18, 2026 | Amazon Web Services | Nvidia | GPU capacity expansion / reservation | AWS regions (global) | >1 million Nvidia GPUs starting 2026 (Blackwell/Rubin architectures cited) AWS blog at Nvidia GTC 2026: deploy more than 1M Nvidia GPUs across AWS regions starting 2026. announced date set to mid-March GTC window (exact keynote day not pinned in the blog slug). Aug 2026 +2M expansion tracked separately as aws-nvidia-gpus-2027-2028. | — | Announced | Link |
| Feb 11, 2026 | Meta Platforms | Self-build | AI / hyperscale data center campus (self-build) | Lebanon, Indiana, US (Boone County) | Designed for 1 GW capacity; >$10B investment cited Meta Feb 11, 2026: groundbreaking on 1GW Lebanon, Indiana campus; investment over $10B. IT vs gross capacity not separated. | $10B | Under construction | Link |